56th Street Is Now a Construction Zone Through 2028. Here's What Arcadia Gets at the End of It.

October 29, 2026

The orange barrels on 56th Street are at the south end, between Thomas Road and Indian School Road. Neighbors had been told to expect them up by Camelback first.

The City of Phoenix began construction on the 56th Street Improvement Project on October 12, 2026. The city's construction notice puts anticipated completion in fall 2028 and says work "will initially begin at the south end of the project, focusing on the area between Thomas Road and Indian School Road." The Arcadia Camelback Mountain Neighborhood Association posted the same start date and south-end sequencing in its October 16 update.

That order matters for anyone who uses the Osborn Road crossing, Arcadia Park or the blocks around them. The stretch that used to be the second half of the plan now gets the first two years of noise. It will probably also be the first place in Arcadia to show what the finished street looks like.

The Plan Was Supposed to Start Up North

When city streets staff presented the project at the ACMNA annual meeting, Arcadia News reported a two-phase approach. Phase 1 covered the 0.9 miles from north of Indian School Road to Camelback Road, and Phase 2 covered the 0.6 miles from Thomas Road to north of Indian School. The city hoped then to start Phase 1 in winter 2025.

Winter 2025 came and went. The city's project page now says construction on both phases begins in October 2026, with completion anticipated in fall 2028. The two geographic phases still exist on paper as separate Capital Improvement Program projects. One contract now covers both, and crews started at the end that was originally scheduled for later.

North segment South segment
Limits Indian School Rd to Camelback Rd Thomas Rd to Indian School Rd
Length, per Arcadia News About 0.9 mile About 0.6 mile
Earlier cost estimate, per Arcadia News About $14 million About $9 million
City project number ST87210049 ST87210047
Original order Phase 1, first Phase 2, second
Where crews started in Oct. 2026 Later First

The Price Landed Almost Exactly Where Neighbors Were Told

The two earlier estimates add up to about $23 million. At its May 20, 2026 meeting, the Phoenix City Council adopted the ordinance to contract with Hunter Contracting Co. The council report names Hunter as the lowest-priced responsive bidder at $23,142,664.40. That came in below the city's own opinion of probable cost of $26,430,460.50. The other responsive bid, from Combs Construction Company, LLC, was $29,468,633.35.

The council report cites volatile material and labor costs and requests a 10 percent contingency, and it sets the contract's ceiling at $25,456,930.40. Spending above the bid amount needs written approval from the Street Transportation Director and the City Engineer. The contract term is 660 calendar days from the notice to proceed, and the project uses federal funds.

The report's scope list explains where the money goes. It covers multi-use paths, lighting, storm drain, landscape, traffic signal improvements, possible pavement preservation and other roadway safety measures.

What the South End Looks Like Right Now

The city's open data list of traffic restrictions, last updated October 24, 2026, shows a partial restriction on 56th Street from Indian School Road to Thomas Road for Street Transportation work. It runs October 19 through November 23 and lists the project hotline.

The same list has two other partial restrictions on this corridor, both from October 22 to November 5. One covers Osborn Road to Camelback Road, and the other covers Cheery Lynn Road to Indian School Road. Both are labeled utility work, and neither carries the project hotline. A lane taper near Indian School in the next two weeks may belong to a utility crew.

Standard project hours are Monday through Friday, 7 a.m. to 4 p.m. The notice also says some night and weekend work may be scheduled when needed to reduce impacts on the community. The city has said more notices will follow as specific work and traffic changes are scheduled.

The Busiest Fall Dates Fall Inside the First Work Zone

The south segment runs past Arcadia Park, on 56th Street at Osborn Road. Several of the area's biggest fall dates fall during the first restriction window there:

  1. Friday, October 30, 4 p.m. The Arcadia High Homecoming Parade starts at Ingleside Middle School, 5402 E. Osborn Road, and ends at Tavan, 4610 E. Osborn Road, as listed in Arcadia News' October briefs. The city's restriction list shows a full closure of Osborn Road from 46th Street to 56th Street that day for a special event.
  2. Saturday, November 7, 1 to 4 p.m. The Arcadia Osborn Neighborhood Association holds its Fall Festival and G.A.I.N. event at Arcadia Park, 56th Street and Osborn. G.A.I.N. stands for Getting Arizona Involved in Neighborhoods, and AONA says the festival is funded by a City of Phoenix block watch grant.
  3. November 7 and 8, 10 a.m. to 4 p.m. The Shemer Arizona Arts Festival at Shemer Art Center, 5005 E. Camelback Road, has work from 40 juried Arizona artists, chalk artists, a Blacksmiths Village, live music and a $5 Interactive Art Zone. It sits west of the corridor, but anyone coming from south Arcadia will probably drive up 56th to reach Camelback.

The festival and the arts weekend both fall on a weekend, outside standard project hours. Since the notice allows some weekend work when needed, check the project page before setting up a booth or planning a drop-off.

What the South End Gets First

The city's list of improvements applies to the whole 1.5-mile corridor, so the Thomas-to-Indian School blocks get the same features as the north segment, only sooner:

  • A continuous multi-use path for bikes and pedestrians on both the west and east sides of 56th Street, 10 to 12 feet wide, meant for younger cyclists, school-age children, families and people on foot
  • A 24-inch storm drain running the length of 56th Street from Thomas to Camelback
  • Low-water-use trees for shade next to the sidewalk and path
  • Upgraded curb ramps and sidewalks to current ADA standards
  • Traffic-calming features meant to reduce speeds

The design legend in the city's roll-plot diagrams lists raised medians, raised intersections, raised pedestrian crossings and traffic chokers among the tools. The plan labels along the route include Osborn, Indian School Road, Lafayette, Exeter, the Arizona Canal, Prince of Peace Lutheran Church and the Church of Jesus Christ. The city's cross-section diagrams show three options: no landscape buffer between the path and traffic, a buffer on one side, or buffers on both sides. The detailed sheets show which blocks get which.

The new storm drain may matter more than anything else on the list. When Arcadia News covered the ACMNA meeting, it described the drain as addressing "long-standing drainage issues along 56th Street." Residents who have driven this street after a monsoon storm will know what that refers to.

Camelback Waits, but Gets the Biggest Change

The north end comes later, and the city calls its change at Camelback Road a complete signal rebuild. According to the project page, residents asked during public engagement for a left-turn arrow onto 56th from eastbound Camelback, and from 56th onto westbound Camelback. The rebuild goes further and includes:

  • Green, solid yellow, red and flashing yellow arrows for every approach
  • A dedicated left-turn lane for northbound 56th Street
  • Pedestrian push buttons and countdown timers on all four approaches
  • New ADA ramps on every corner

The construction notice says signals will be updated at five intersections in all. The roundabout at Exeter Boulevard is still listed on the project page as a place for "possible changes or improvements." The October notice describes it more firmly as improvements to improve safety and traffic flow at that intersection.

When the project was presented, District 6 Councilman Kevin Robinson told Arcadia News:

"I'm beyond excited to see the 56th Street project finally moving forward – it's been a long time coming!"

Final design started in May 2022, so the project took more than four years to reach construction. With crews starting at Thomas Road, the first finished paths, trees and calmer intersections are likely to appear between Thomas and Indian School. The Camelback signal comes later.

You can reach the project team at 623-825-3444 or [email protected], or sign up for construction notices on the city's 56th Street page.

If you own along 56th Street or a few blocks off it, and you're wondering how two years of construction followed by a rebuilt street could affect your plans, The Bray Team can go over it with you block by block. Request your home valuation and we'll take the 56th Street schedule into account.